Restructuring and technical expansion of the waste treatment plant for 2,000 residents and atmospheric water treatment including sewer system restructuring of the Waldthurn area

waldthurn_wappen Total investment: approx. DM 3.6 million
Project start: May 1999
Achieved cost savings: approx. DM 2.5 million

Sewer system management study for the sewer system and atmospheric water treatment plants of the Waldthurn area.

Project start: 2001

Determination of the total surface area by a survey with residents’ participation; Updating of surface area statistics; hydrodynamic sewer system computation.

Cost reduction objective: Avoidance of an expansion of the community sewer system requiring an investment in the millions.

wt1 wt2 wt3